Governance question from CRC

Jitesh, I selected a although b and c seem to be correct as well. What is the best choice? Thank you, darryl

You a...

 

Quality Audit

Jitesh, I selected a after stuggling with answers a abd b. Our field Safety Specialist complete a safety checklist every day the rig is working. An audi...

 

Program Monitoring and Control question from CRC

Jitesh, I selected c by invalidating the other three choices. Nevertheless, can you direct me to where this is stated in the SPM as the question indicat...

 

Financial Management question from CRC

Jitesh, I selected a because contingency reserves are managed by the program manager. The other three choices did not support my experience, which is th...

 

Tools vs Techniques Question from CRC

As the program manager for the new landfill program for your county, you are facing a number of challenges. You have identified a large number of stake...

 

Environmental Factors Question from CRC

Jitesh, I strugged between choices b and c becasue the correct answer does not align with the SPM wording. Pg. 30 of SPM cites "cultural diversity" and ...

 

Stakeholder Engagement Question (CRC) from Darryl

Jitesh, while I selected c, b seemed to be the first action. Which is correct?

I am perplexed why author wrote the first sentence of this questio...

 

Impact Analysis (CRC question)

The CRC menitions as a choice in several questions "determine impact analysis." I do not have an electronic version of the SPM in order to search where ...

 

Stakeholder Engagement Question from CRC (darryl)

Jitesh, I chose a, Nevertheless I was not on firm ground given choice d. Which one is correct and why? Thank you, darryl

Your professional associa...

 

Infrastructure Question from CRC (darryl)

Jitesh, I chose b after narrowing down between a and b. Each answer has merit, which one best addresses the question? Thank you, darrryl 

 

Risk Management Question from CRC (Darryl)

Jitesh, I chose b becasue my role was sponsor and sponsor provides the resources (contingency funding in this). Nevertheless, d and c are key questions ...

 

Program Strategy Alignment - question from CRC (Darryl)

Assume your executive management team has requested that a standard process be put in place for a business case for new programs and projects to pursue in ...

 

Program Communications question CRC

Because your program has the highest priority in the organization's portfolio, your Governance Board meets each month, and each member receives a weekly...

 

What is the correct high level sequence of events (tasks) for the Strategic Domain since the Standard and ECO are not aligned?

Reconcile ECO & Standard v3:
1. Strategic Plan (done by Portfolio Review Board)
2. Initial Assessment (start Business Case & Feasibili...

 

Are you Eligible For PgMP (Program Mgmt. Professional) Certification?

 

Do you have a Secondary Diploma (Hig...

Poll of the Week

What should PGB review for approval of program to proceed to closure?

Benefits Realisation Plan
Program Management Plan
Program Charter
Performance Report
Vote

Voting ends on 06/30/2019